Abstract

Objective As the development and utilization of urban underground space advances towards the three-dimensional and multi-dimensional direction, there are more and more over-crossing and under-crossing urban rail transit projects. Among them, the close under-crossing construction of new stations with large cross-section has a significant impact on the surrounding environment. Therefore, it is urgent to carry out an in-depth study on the ground settlement and deformation law of existing stations during the new station construction process closely under-crossing existing stations by Pile-Beam-Arch (PBA) method. Method Based on the actual engineering case of Beijing Metro Line 6 Pinguoyuan Station, which closely under-crosses the existing station with same name on Metro Line 1, the law of ground settlement and deformation of the existing station is analyzed by adopting numerical simulation method in the study. By comparing the actual monitoring data, the actual situation of ground settlement and deformation of the existing station during the construction process is further verified, and the numerical simulation results are compared and analyzed with the measured data. Result & Conclusion The most unfavorable stages for ground settlement and existing structure deformation are the guide hole excavation stage and the second lining arch stage of PBA method. After the completion of second lining arch construction, both the ground settlement and the deformation of the existing structure show rebound phenomenon. In addition, the stiffness of the existing station has a significant inhibiting effect on the ground settlement above, which is manifested in the fact that the ground settlement value of the overlapping section is smaller than that of the non-overlapping section. The deformation of the existing station structure caused by new station constructed with PBA method is mainly the rigid body displacement, while it caused track structure deformation is mainly the overturning deformation, which is locally manifested as rigid body displacement.

Authors and Affiliations

Mingyang XU, Haitao WANG, Jiangtao TIAN, Zhiwei ZHANG, Qiang YOU

Keywords

Related Articles

Deep Energy-saving and Consumption Reduction Strategies for Urban Rail Transit

Objective With the increase in urban rail transit operational lines and operating hours, electrical energy consumption rises annually. To reduce energy consumption and operational costs, it is essential to conduct in-dep...

Research on the Impact of Metro Station Illuminance on Passengers′ Emotion and Visual Cognition

Objective Proper illuminance environment plays an important role in improving the service level of metro stations, ensuring the safety of passenger evacuation and promoting the sustainable development of public transport...

In-depth Security Defense Strategy for Rail Transit Vehicle Communication Network System

Objective The vehicle communication network contains a wide variety and a large quantity of internal and external network communication interfaces, resulting in continuous rising of the vehicle information security risks...

Architecture Design Scheme of Signal Centralized Monitoring System Based on Cloud Computing Technology

[Objective] To meet the development needs of railway electricity work monitoring services and address issues such as high coupling degree, lengthy deployment time, and high construction and operational costs in conventio...

Evolution Characteristics and Implications of Seoul Metropolitan Area Rail Transit

Objective The comprehensive understanding of rail transit evolution in developed metropolitan areas abroad is beneficial for the scientific construction of rail transit network and the rational scheduling of construction...

Download PDF file
  • EP ID EP749215
  • DOI 10.16037/j.1007-869x.2024.10.012
  • Views 95
  • Downloads 1

How To Cite

Mingyang XU, Haitao WANG, Jiangtao TIAN, Zhiwei ZHANG, Qiang YOU (2024). Research on the Settlement Law of the Ground and Existing Stations in the Close Under-crossing Construction of Subway Station. Urban Mass Transit, 27(10), -. https://europub.co.uk./articles/-A-749215