Hazards of Waterproof Board Cutting Secondary Lining in Operating Tunnel and Remediation Schemes
Journal Title: Urban Mass Transit - Year 2024, Vol 27, Issue 10
Abstract
Objective With the acceleration of tunnel construction in China, various diseases in operating tunnels become increasingly prominent. Despite of many in-depth researches by scholars on various diseases, that on the hazards of waterproof board cutting secondary lining is still insufficient. Therefore, it is necessary to deeply explore the secondary lining cutting hazard in operating tunnels and propose effective remediation schemes. Method Based on the waterproofing and force mechanism of waterproof boards, numerical simulation technology is used to systematically study the secondary lining cutting hazard in operating tunnels. Focusing on the waterproof board arch bending moment, the Mises stress and the lining displacement under different circumferential and longitudinal cutting lengths, the changing law of their key indicators are emphatically analyzed. On this basis, a new remediation design scheme is proposed, and the rationality-superiority of the remediation design scheme is verified by comparing the changes in the lining structure vault displacement before and after the waterproof board remediation. Result & Conclusion With the increase in the circumferential and longitudinal cutting lengths of the waterproof board, the arch bending moment, the lining stress and displacement all show a significant growth trend. In particular, the longitudinal cutting length of the waterproof board has a more significant impact on the three indicators such as lining displacement. Through comprehensively analyzing the sudden change areas of bending moment, stress and displacement, it is found that when the waterproof board circumferential and longitudinal cutting lengths are in the range of 2~3 m, the impact on stress and deformation of the lining structure is most unfavorable.
Authors and Affiliations
Yunfei SHI, Xingwang GONG, Zhenqi YU, Lun GONG, Zelin LIU, Xiaoti CUI
Optimization of Metro Tunnel Maintenance Strategy Based on Improved Particle Swarm Algorithm
[Objective] Maintenance strategy is the key factor influencing the lifetime service performance and maintenance cost of metro tunnel. Therefore, it is essential to develop more suitable optimization algorithms for mainte...
Adjustment of Nantong Urban Rail Transit Network Planning after Introducing Important Regional Transportation Infrastructure
Objective Under the background of regional integration of Yangtze River Delta, the introduction of important regional transportation infrastructures such as the new airport (hub) station in Nantong will not only greatly...
Effect Analysis of Excavation and Unloading of Deep Foundation Pit in Soft Soil Stratum on Pile Foundation of Underground Station
Objective In the excavation process of deep foundation pit of underground station in deep soft soil stratum, excavation and unloading of the overlying soil in the pit will obviously impact the previously constructed supe...
Optimization Analysis of Treatment Scheme for Metro Tunnel Base Waterlogged Collapsible Loess Formation
Objective To study the optimization measures for treating waterlogged collapsible loess stratum, it is necessary to investigate the deformation characteristics of tunnel structures after loess collapse by waterlogging. M...
Research on the Settlement Law of the Ground and Existing Stations in the Close Under-crossing Construction of Subway Station
Objective As the development and utilization of urban underground space advances towards the three-dimensional and multi-dimensional direction, there are more and more over-crossing and under-crossing urban rail transit...