Optimising Cost Savings on well Clean up and Test Services: Case-Niger Delta Wells

Abstract

In this work, the optimisation of cost savings on well clean up and test services using Niger Delta wells as case are presented. Four wells drilled into the same reservoir are used as cases. Well clean up and test services were carried out on the four wells: ZX8, ZX9, ZX10 and ZX11. The highlights of the campaign included: cleaning up the wells of any drilling fluid, debris and completion fluid without damaging the ESS up to 50MMscf/d; conducting multi-rate test(s) to a maximum rate of 50MMscf/d respectively on all four (4) wells; acquiring surface data to facilitate further evaluation of wells’ performance. Initial costs planning for the campaign was done using the old contract in place for the provision of well clean up and test. The old contract was thoroughly reviewed and closer evaluations on its activities were done, from which new planned costs were developed. The wells were worked on based on the optimised costs from the new contract. Two important parameters: Costs Ratio (CR) and Mean Cost Ratio (MCR) are introduced which are used to evaluate the extent of cost optimisation for the project on the four wells. From the analyses, MCR for each of the four wells is far less than 1 which signifies very high level of cost optimization. The cost of operations on well ZX10 were optimised the most as it is seen that the MCR for well ZX10 is the lowest. The various proactive steps taken to optimise costs of the well clean up and tests services project which include: effective planning; effective operations surveillance; emphasis on quality assurance and control; etc, and the gains from appropriate cost optimization are also highlighted and properly described

Authors and Affiliations

Nnaemeka Ohia, Charley Anyadiegwu, Chukwuemeka Muonagor

Keywords

Related Articles

Compositional Simulation of the Effect of Water Injection on Gas Condensate Reservoir Performance

It is well recognized that the liquid dropout in the reservoir from a gas condensate reservoir below dew point pressure does not only reduce the ultimate recovery of gas, but can also reduce the gas well deliverability....

Waterflooding in Niger Delta Oil Reservoir Systems: Concept and Analysis

This research work looked at the concept and analysis of waterflooding as a means of enhancing oil production at commercial scale from oil reservoirs in the Niger Delta, south of Nigeria. It covers the linear flow profil...

Optimization of Gas Well Performance through Well Capacity Prediction using Systems Analysis Approach

Analyses of the variables that affect the performance of flowing gas wells were carried out in this project to optimize production of wells U300, U400 and U500 whose production from onset was less than 60% of the expecte...

Optimising Cost Savings on well Clean up and Test Services: Case-Niger Delta Wells

In this work, the optimisation of cost savings on well clean up and test services using Niger Delta wells as case are presented. Four wells drilled into the same reservoir are used as cases. Well clean up and test servic...

Intellectual Capital and Organizational Performance of Oil Companies in Port Harcourt, Nigeria

The study sought to examine the relationship between intellectual capital and organizational performance in oil companies in Port Harcourt, using a cross-sectional survey design; the data for the study was generated from...

Download PDF file
  • EP ID EP668488
  • DOI -
  • Views 100
  • Downloads 0

How To Cite

Nnaemeka Ohia, Charley Anyadiegwu, Chukwuemeka Muonagor (2019). Optimising Cost Savings on well Clean up and Test Services: Case-Niger Delta Wells. JOURNAL OF ADVANCED RESEARCH IN PETROLEUM TECHNOLOGY & MANAGEMENT, 5(1), 17-23. https://europub.co.uk./articles/-A-668488